PMP Exam Prep · Earned Value Management
CPI & SPI Complete Study Guide
Explainer · Worked Example · Interactive Calculator
PV
Planned Value
What did we plan to finish by today?
The budgeted cost of the work that was scheduled to be done by now. It's your plan.
EV
Earned Value
What have we actually accomplished?
The budgeted cost of the work that was actually completed. It's your real progress.
AC
Actual Cost
How much money did we actually spend?
The real money spent to complete the work so far. It's your actual spending.
🏗️ Imagine you are building a house. Today is the halfway point of the project.
PV
You planned to have the foundation and walls done by today. That work was budgeted at $50,000. That is your PV.
EV
But you only finished the foundation (not the walls). That foundation was budgeted at $30,000. That is your EV — you "earned" only $30k worth of work.
AC
To build just the foundation, you actually spent $40,000 (more than budgeted!). That is your AC — the real money out of your pocket.
Project progress at the halfway checkpoint ($50k total budget)
PV — Planned$50,000
EV — Earned (actual progress)$30,000
AC — Actual cost spent$40,000
EV < PV → behind schedule  |  AC > EV → over budget — double trouble!
CPI — Cost efficiency
EV ÷ AC
$30k ÷ $40k = 0.75 → Over budget ⚠️
SPI — Schedule efficiency
EV ÷ PV
$30k ÷ $50k = 0.60 → Behind schedule ⚠️
> 1.0 ✓
Good — under budget or ahead of schedule
< 1.0 ✗
Bad — over budget or behind schedule
🏗️ Construction project
Over budget, behind schedule
💻 Software project
Under budget, behind schedule
📦 Event planning
Over budget, ahead of schedule
🚀 Marketing campaign
Under budget, ahead of schedule
1
Identify your three values
2
Calculate CPI (Cost Performance Index)
Divide EV by AC. This tells you how much value you got for every $1 spent.
3
Calculate SPI (Schedule Performance Index)
Divide EV by PV. This tells you how much work you did vs. what was planned.
4
Calculate the variances (CV and SV)
Same pairs, but subtract instead of divide. This tells you how many dollars off you are — not just the ratio.
5
Interpret the results
CPI — Cost Index
EV ÷ AC
Ratio · compare to 1.0
SPI — Schedule Index
EV ÷ PV
Ratio · compare to 1.0
CV — Cost Variance
EV − AC
Dollars · compare to 0
SV — Schedule Variance
EV − PV
Dollars · compare to 0
> 1.0  /  positive ✓
Good — under budget or ahead
< 1.0  /  negative ✗
Bad — over budget or behind
Type exact values from a practice question, or drag the sliders to explore.
PV
Planned Value
$
Work planned by now
EV
Earned Value
$
Work actually done
AC
Actual Cost
$
Money actually spent
Quick fill:
CPI — Cost
0.80
01.02.0
Over budget
SPI — Schedule
0.80
01.02.0
Behind schedule
CV — Cost Variance
EV − AC
-$20
SV — Schedule Variance
EV − PV
-$20
Index = ÷ (Ratio)
CPI · SPI
Answer is a number like 0.85 — no dollar sign. Tells you efficiency. Compare to 1.0.
Variance = − (Subtract)
CV · SV
Answer is a dollar amount like -$5,000. Tells you how much. Compare to 0.
💰
CPI = EV ÷ AC — "Did I get my money's worth?" EV on top = value received. AC at the bottom = money spent. Below 1 = you spent more than you earned.
🕐
SPI = EV ÷ PV — "Am I on time?" EV on top = work done. PV at the bottom = work planned. Below 1 = you did less than planned.
CV and SV always start with EV too. CV = EV − AC. SV = EV − PV. Same pairs as the indexes — just subtract instead of divide. Negative = bad.
💡
EV is always first in every EVM formula. Learn that one rule and you'll never write a formula backwards. 1.0 for indexes, 0 for variances — that's your baseline.